:quality(80))
Hygienic Lifting System for a Food Processing Production Line
Verlinde supplied a fully stainless steel hoist solution meeting food-grade hygiene requirements, enabling continuous operation in a high-care production environment.
Manufacturing industry
DOSSOT and Somiram, both Verlinde partners, delivered a customized overhead crane solution for DRUMEL Industrie, enabling the installation and operation of a new machining center in a highly constrained space.
:quality(80))
To support a new machining center investment at DRUMEL Industrie, Verlinde partners DOSSOT and Somiram delivered a customized lifting solution designed for a highly constrained installation environment. The project was intended to support DRUMEL Industrie’s production of larger and heavier parts while ensuring safe and efficient machine handling.
The project presented a significant technical challenge due to the extremely limited space available. The new machining center had already been ordered, and the installation area allowed only 1 meter of clearance above the machine for a 6.3-tonne crane. As a result, a standard crane solution could not meet the requirements. In addition, the project required a customized power supply system adapted to the industrial environment.
:quality(80))
DOSSOT installed a 6.3-tonne overhead travelling crane with a span of 13,070 mm, fitted with a Verlinde EUROBLOC VT204 double-girder electric wire rope hoist. The double-girder configuration was selected to distribute the load between two rails and optimize hook height.
To gain additional height, the crane beams were directly inserted into the building walls. The solution also included a load limiter with two Maximum Working Capacity (MWC) thresholds, a programmed restricted travel area to prevent collisions between the hook and the machine, and a power supply system designed with an energy chain to minimize exposure to splinters and dust.
:quality(80))
Successful installation of a 6.3-tonne overhead travelling crane in a space with only 1 meter of clearance above the machining center.
Optimized hook height through the use of a Verlinde EUROBLOC VT204 double-girder electric wire rope hoist.
Additional height gained by inserting the crane beams directly into the building walls.
Enhanced safety through dual Maximum Working Capacity (MWC) thresholds and a programmed restricted travel area.
Reduced exposure of the power supply system to splinters and dust through the use of an energy chain.
Smooth project execution through coordination between DOSSOT and Somiram.
Increased production capacity, enabling DRUMEL Industrie to handle larger and heavier parts.
Long-term reliability and performance supported by DOSSOT's maintenance services.
:quality(80))
Get Verlinde's latest product launches, certifications and industry news delivered directly to your inbox.
:quality(80))
Verlinde supplied a fully stainless steel hoist solution meeting food-grade hygiene requirements, enabling continuous operation in a high-care production environment.